Construction Contract Tracker
The Illinois Tollway is committed to sharing information regarding construction contracts and expenditures. The Construction Contract Tracker provides public access to current contract records and information about project status.
Explanation of Terms
- Contract Number: Number assigned to contract
- Description: Scope of work
- Notice to Proceed: Date in which contractor is able to begin work related to the contract
- Start Date: Date in which contractor is on-site and beginning work
- Contract Completion Date: Estimated completion date
- Contract Award Amount: Original amount Board of Directors approved to be spent on contract
- Contract Authorized Amount: Amount approved based on original award amount and any change orders or extra work orders applied to contract
- Board Approval Date: Date in which the Illinois Tollway Board of Directors approved the contract
- DBE Advertised Goal: Diversity staff establishes specific numerical contract goals for participation of DBE/MBE/WBE certified firms on construction contracts and professional service contracts
- Project Phase: Phase the contract is currently in
- Route: Illinois Tollway corridor in which contract is located
- Location: Contract limits defined by mile posts
- County: County(ies) in which the contract is located
- Prime Contractor: Contractor responsible for the completion of the contract
- Earned to Date: Amount which has been paid out by the Illinois Tollway on the contract
- Percent Complete: Percentage based on earned to date amount compared to the authorized amount
- Extra Work Order: Adding new work to a project that was not included in the original contract
- Change Order: Adding or subtracting quantities of work or materials on a contract