Construction Contract Tracker

The Illinois Tollway is committed to sharing information regarding construction contracts and expenditures. The Construction Contract Tracker provides public access to current contract records and information about project status.

[Explanation of Terms]

Contract Name and Number               Award
Amount
Map
Tri-State Tollway (I-294/I-94/I-80) Construction Projects
Wetland Mitigation
I-07-5230RR
$2,215,147 no map
Bioswale Stormwater
I-07-5539
$5,218,725 View Map
Bridge Rehabilitation - IL Route 394 to 167th Street
RR-10-5613
$561,821 no map
Tri-State Tollway Landscaping
RR-10-5619
$699,515 no map
Tri-Level Bridge Rehabilitation
RR-08-5569
$13,120,363 View Map
Bridge Rehabilitation – Chicago Road to 88th Street and Everett Road
RR-09-5591
$1,568,532 View Map
Intermittent Pavement Repairs
RR-11-5626
$2,621,946 no map
Roadway and Bridge Rehabilitation - NB 95th Street to Cermak Road
RR-11-5634
$28,549,077 no map
Roadway and Bridge Rehabilitation - SB 95th Street to Cermak Road
RR-11-5635
$26,662,922 no map
Roadway and Bridge Rehabilitation - Cermak Road Toll Plaza to the Bensenville Bridge
RR-11-5636
$28,841,879 no map
Roadway and Bridge Rehabilitation - Bensenville Bridge to Balmoral Avenue
RR-11-5637
$8,884,335 no map
Pavement Rehabilitation - Half Day Road to Lake Cook Road and Buckley Road to Rockland Road
I-05-5430
$5,439,073 no map
I-294/I-57 Interchange, Bridge Reconstruction Over 147th Street
RR-12-4035
$7,705,273 View Map
Veterans Memorial Tollway (I-355) Construction Projects
No active construction contracts    
Reagan Memorial Tollway (I-88) Construction Projects
Roadway and Bridge Rehabilitation - IL Route 251 to Annie Glidden Road
RR-10-5614
$23,608,677 no map
Roadway and Bridge Rehabilitation - Annie Glidden Road to IL Route 56
RR-10-5615
$30,739,236 no map
Rebuild and Widen, Deerpath Road to Illinois Route 56
I-11-5624
$9,408,707 View Map
Jane Addams Memorial Tollway (I-90) Construction Projects
Roadway and Bridge Rehabilitation - Newburg Road to Sandwald Road
RR-10-5617
$28,988,554 View Map
Roadway and Bridge Rehabilitation - Elgin Toll Plaza to Barrington Road
I-09-5588
$35,829,249 View Map
Intermittent Pavement Repairs
RR-11-5627
$6,258,949 no map
I-90/Illinois Route 47 Interchange
I-11-4000
$35,708,680 View Map
Systemwide Construction Projects
Systemwide Pavement Striping
RR-10-9012
$1,349,942 no map
Landscaping I-294 North Section
RR-10-5620
$432,070 no map
Systemwide Landscaping
RR-10-5621
$516,365 no map
Landscaping I-294 South Section
RR-10-5622
$347,325 no map
I-88/I-355 Intermittent Pavement Repairs
RR-11-5625
$3,539,564 no map
Violation Enforcement System Camera Wash System
RR-11-5628
$2,205,009 no map
Systemwide Pavement Striping
RR-11-9106R
$1,094,866 no map
Salt Storage Dome Replacement
RR-11-9108
$871,861 no map
Systemwide Signage
RR-11-9117
$943,955 no map
Systemwide Facilities Repairs
RR-12-9121
$3,597,432 no map

[Back to top]


Explanation of Terms

  • Contract Number: Number assigned to contract
  • Description: Scope of work
  • Notice to Proceed: Date in which contractor is able to begin work related to the contract
  • Start Date: Date in which contractor is on-site and beginning work
  • Contract Completion Date: Estimated completion date
  • Contract Award Amount: Original amount Board of Directors approved to be spent on contract
  • Contract Authorized Amount: Amount approved based on original award amount and any change orders or extra work orders applied to contract
  • Board Approval Date: Date in which the Illinois Tollway Board of Directors approved the contract
  • DBE Advertised Goal: Diversity staff establishes specific numerical contract goals for participation of DBE/MBE/WBE certified firms on construction contracts and professional service contracts
  • Project Phase: Phase the contract is currently in
  • Route: Illinois Tollway corridor in which contract is located
  • Location: Contract limits defined by mile posts
  • County: County(ies) in which the contract is located
  • Prime Contractor: Contractor responsible for the completion of the contract
  • Earned to Date: Amount which has been paid out by the Illinois Tollway on the contract
  • Percent Complete: Percentage based on earned to date amount compared to the authorized amount
  • Extra Work Order: Adding new work to a project that was not included in the original contract
  • Change Order: Adding or subtracting quantities of work or materials on a contract