Tollway : Traffic & Construction : Projects by Roadway : Tri-State Tollway (I-94/294/80) : North Tri-State (I-294/94) Rebuild & Widen Project
 
Tri-State Construction banner


Overview: Dempster Street to the Wisconsin State Line - Rebuild and Widen

Project Map
Project Fact Sheet

Jump to a page section:
update | impact | schedule | purpose | news

The Illinois Tollway is rebuilding and widening the North Tri-State Tollway (I-294/I-94) throughout a 39-mile corridor to provide congestion relief. The project includes reconstructing and widening to four lanes in each direction of the North Tri-State Tollway between Dempster Street and IL Route 173. Four lanes are now open in each direction between Grand Avenue and IL Route 173. Work to reconstruct the roadway north of IL Route 173 to Russell Road and resurface pavement from Russell Road to the Wisconsin state line is complete. This work is part of the Tollway's Congestion-Relief Program to reduce travel times.

Update – Latest Construction Info

[Download today's daily report of system-wide lane closures...]

Three lanes in each direction are on new pavement on the two right lanes and right shoulder as construction work is nearing completion on the median and new fourth lanes in each direction.

Update – Bridge Construction

Several bridges are being rebuilt and lengthened to accommodate mainline construction. Bridge work is scheduled at Ballard Road, Golf Road, Central Road, Milwaukee Avenue, Lake Avenue, Sanders Road, Half Day Road, Rockland Road (IL Route 176), and Washington Street. Bridge work is complete at Lake Cook Road, Willow Road, Belvidere Road, Rosecrans Road (IL Route 173), Grand Avenue, O'Plaine Road, and at U.S. Route 41

Half Day Road – All traffic is now traveling on the newly reconstructed eastbound side of the bridge while the westbound side of the bridge is closed for reconstruction work.

Rockland Road– One lane in each direction on Rockland Road under I-94 is closed for bridge abutment work.

Crossroad bridge construction is being staggered to reduce inconvenience. The bridges remain open with staged traffic and reduced lanes. The Tollway is coordinating bridge work with IDOT, Cook County , and Lake County to minimize the impact to local roads, but delays are expected.

[RETURN TO TOP/MENU]

Minimizing Impact to Reduce Delays

Three lanes of traffic will remain available in both directions during daytime hours throughout this project. Lane closures will be permitted off-peak only to minimize the impact to traffic.

[RETURN TO TOP/MENU]

Work Zone Safety
Construction zone speed limits are in effect in all construction zones 24/7 and drivers should continue to watch for changing traffic patterns and use caution, especially when workers are present. Reduced speed limits will be in place on bridges under construction, while a 45 m.p.h. speed limit will be in place on the mainline. See the Tollway’s Work Zone Safety page.

[RETURN TO TOP/MENU]

Schedule
  • 2007 – Southbound Rebuild & Widen work from the Wisconsin state line to Grand Avenue completed in late 2007.
  • 2008 – Northbound Rebuild & Widen work from Grand Avenue to IL Route 173, rebuild work from IL Route 173 to Russell Road , and resurfacing work from Russell Road to the Wisconsin State Line completed.
  • 2008 – Southbound Rebuild & Widen work from Grand Avenue to Half Day Road and from Lake Cook Road to Dempster Street completed.
  • 2009 – Work scheduled in northbound lanes from Dempster Street to Lake Cook Road and from Half Day Road to Grand Avenue .
  • 2010 – All work completed.

[RETURN TO TOP/MENU]

Purpose – Pertinent Details on Why and How

Rebuilding and widening the section of road to four lanes in each direction from Dempster Street to IL Route 173 and rebuilding from IL Route 173 to Russell Road will provide congestion relief and reduce travel times. The Tollway is coordinating work with local, county and state transportation officials on work to reconstruct I-294/I-94. When Rebuild & Widen Projects on the north, central and south segments are complete, the Tri-State Tollway will provide four lanes in each direction from Indiana , up to the north end of the system near the Wisconsin state line.

[RETURN TO TOP/MENU]

News
  Results: Items 1 - 4 of 13  Next 4
  
28-AUG-09 08/28/2009 Temporary Local Access Ramp Lake Forest Business Park to Northbound Tri-State Tollway (I-94) to Close August 29
Design Work Underway for Parking Lot Expansion for Commercial Vehicles
22-JUL-09 07/22/2009 Tri-State Tollway (I-294) Traffic Shifts to New Pavement Begins Tonight and Ends in August
Touhy Entrance Ramp to Southbound Tri-State Tollway (I-294) to Reopen As Rebuild & Widen Project Progresses
27-FEB-09 02/27/2009 Construction Express Lanes Open This Weekend on North Tri-State Tollway (I-94/I-294) rebuild & widen projects
Traffic Shifts Tonight Between Dempster Street and Lake Cook Road; On Monday, March 2 from Touhy Ave. to Balmoral Ave., And on Wednesday, March 4, from Half Day Road to Grand Ave.
23-FEB-09 02/23/2009 Northbound Construction Express Lane Opens this Week on North Tri-State Tollway (I-294/I-94) Rebuild & Widen Projects
Traffic Shift for Construction Scheduled Overnight Wednesday, Feb. 25 Between Dempster Street and Lake Cook Road

[RETURN TO TOP/MENU]

Updated November 20, 2009