Rebuild & Widen: Working hard to reduce your travel time safely and swiftly-now and into the future.
Traffic and Construction Menu Header
Tollway : Traffic & Construction : Projects by Roadway : Tri-State Tollway (I-94/294/80) : Central Tristate Rebuild & Widen
 
Tri-State Construction banner


OVERVIEW: Balmoral Avenue to Demptser Street - Rebuild and Widen

Project Map
Project Fact Sheet

Jump to a page section:
update | impact | schedule | purpose | news

The Illinois Tollway has rebuilt and widened to four lanes the 4.5-mile section of the Central Tri-State Tollway between Balmoral Avenue and Dempster Street in order to provide congestion relief and reduce travel times for Tollway customers. This work was part of the Tollway's Congestion-Relief Program to reduce travel times.


Update – Latest Construction Info

[Download today's daily report of system-wide lane closures...]

Four lanes in both directions are now open on new pavement between Balmoral Avenue and Dempster Street. Some minor punch list work is scheduled during off-peak hours to complete sewer cleaning and installation of rumble strips. Weather-dependant work such as landscaping will resume in spring but will not impact traffic.

Update – Bridge Construction
Several bridges were rebuilt and lengthened to accommodate mainline construction. Work included bridges at Interstate I-90, Higgins Road, Devon Avenue, Des Plaines River Road, Touhy Avenue, Des Plaines River, Oakton Street, Algonquin Road, Busse Highway, Northwest Highway and Dempster Street.

[RETURN TO TOP/MENU]

Minimizing Impact to Reduce Delays

Three lanes of traffic remained available in both directions during peak travel times throughout this project. Lane closures were permitted off-peak only, to minimize the impact to traffic. Please see our Daily Lane Closures for specific daily lane closures per project.

[RETURN TO TOP/MENU]

Work Zone Safety

Construction zone speed limits are in effect in all construction zones 24/7 and drivers should continue to watch for changing traffic patterns and use caution, especially when workers are present. A 45 m.p.h. speed limit will be in place on the mainline. See the Tollway’s Work Zone Safety page.

[RETURN TO TOP/MENU]

Schedule
  • Fall 2006 – Northbound work began from Touhy Avenue to Dempster.
  • Late 2007 – Northbound lanes from Touhy Avenue to Dempster completed.
  • Spring/Summer 2008 – Northbound complete, southbound work began.
  • Spring 2009 – Counterflow configuration in place southbound, Touhy to Balmoral.
  • Completion by end of 2009.

[RETURN TO TOP/MENU]

Purpose – Pertinent Details on Why and How

Rebuilding and widening this section of road to four lanes will provide congestion relief and reduce travel times. The Tollway is coordinating work with local, county and state transportation officials on work to reconstruct I-294 in this section. When Rebuild & Widen Projects on the north, central and south segments are complete, the Tri-State Tollway will provide four lanes in each direction from Indiana , up to the north end of the system near the Wisconsin state line.

[RETURN TO TOP/MENU]

News
  Results: Items 1 - 4 of 19  Next 4
  
18-DEC-09 12/18/2009 - Central and North Tri-State Tollway (I-94/I-294) Rebuild & Widening Projects Complete
20-AUG-09 08/20/2009 Lane Reduction Begins this Week at I-190/O’Hare Interchange for Central Tri-State Tollway (I-294) Rebuild & Widen Project
Westbound Ramp Reduced for Patching and Resurfacing, Delays Expected
18-AUG-09 08/18/2009 Lane Reduction Begins This Week at I-190/O’Hare Interchange for Central Tri-State Tollway (I-294) Rebuild & Widen Project
Westbound Ramp Reduced for Patching and Resurfacing, Delays Expected
22-JUL-09 07/22/2009 Tri-State Tollway (I-294) Traffic Shifts to New Pavement Begins Tonight and Ends in August
Touhy Entrance Ramp to Southbound Tri-State Tollway (I-294) to Reopen As Rebuild & Widen Project Progresses

[RETURN TO TOP/MENU]

Updated December 21, 2009