Illinois Tollway Logo
EN ESPAŃOL
Rebuild & Widen: Working hard to reduce your travel time safely and swiftly-now and into the future.
Traffic and Construction Menu Header
Tollway : Traffic & Construction : Projects by Roadway : Veterans Memorial Tollway (I-355) : I-355 Resurface 75th to Ogden
 
I-355 Construction banner


75th Street to Ogden Avenue - Resurface and Widen

Project Fact Sheet
Project Map

Jump to a page section:
update | impact | schedule | purpose | news

The Illinois Tollway has completed the project to resurface and widen a 4-mile section of the Veterans Memorial Tollway (I-355) between 75 th Street and Ogden Avenue . This work is part of the Tollway's Congestion-Relief Program to reduce travel times.

[Download today's daily report of system-wide lane closures...]

Update – Four New Southbound Lanes Open
The newly completed fourth southbound lane between Ogden Avenue and 75 th Street and the new fourth northbound lane at the 75 th Street Interchange have opened.

Work on Ramps, Local Crossroad Bridges Complete
Ramp resurfacing work at the Ogden Avenue , Maple Avenue , 63 rd Street , and 75 th Street interchanges is complete. Bridge deck widening work on the I-355 Bridges over the Burlington Northern Santa Fe Railroad, Jackson Drive , and over Hitchcock Avenue is complete.

[RETURN TO TOP/MENU]

Minimizing Impact to Reduce Delays

Work was scheduled during off-peak and overnight hours to minimize the impact to traffic. Three lanes of traffic were maintained during daytime hours.

Work Zone Safety

Construction work zone speed limits are in effect in all construction zones 24/7 and drivers should continue to watch for changing traffic patterns and use caution, especially when workers are present. Remember to drive safely in work zones and abide by the 45 m.p.h. speed limit on the mainline. See the Tollway’s Work Zone Safety page for more information.

[RETURN TO TOP/MENU]

Schedule
  • 2008 – Work to resurface and build a fourth northbound lane between 75 th Street and Ogden Avenue completed.
  • 2009 – Resurface and widening work scheduled southbound from 75 th Street to Ogden Avenue and northbound at the 75 th Street interchange.
  • Late 2009 – Work completed on I-355 Resurface & Widen from 75 th Street to Ogden Avenue .

[RETURN TO TOP/MENU]

Purpose – Pertinent Details on Why and How

The Resurface & Widen Project included resurfacing the existing roadway originally opened in 1989 with a 4-inch asphalt overlay and construction of a new fourth lane in each direction from Ogden Avenue to 75 th Street to accommodate increased traffic, due in part to the completion of the I-355 South Extension from I-55 to I-80 in 2007. Average daily traffic along the segment of roadway has grown from about 110,000 vehicles daily in 2007 to as high as 136,000 daily vehicles in 2008.

[RETURN TO TOP/MENU]

News
  Results: Items 1 - 4 of 4
  
22-OCT-09 10/22/2009 Westbound Veterans Memorial Tollway (I-355) Resurface & Widen Project Completion Brings New Lanes and Smooth Pavement
4 New Southbound Lanes to Open by Saturday Morning; Northbound Work Completed at 75th Street Interchange
19-AUG-09 08/19/2009 Southbound Traffic Shift Scheduled for Veterans Memorial Tollway (I-355) Resurface & Widen Project
Traffic Will Move to New Pavement Between 63rd Street and 75th Street; Work Begins to Rebuild Inside Lanes
16-OCT-08 10/16/2008 Northbound Traffic Shifts to New Pavement for Veterans Memorial Tollway (I-355) Resurface & Widen Project
Fourth Lane to Open by Late Fall Between 75th Street and Ogden Avenue
17-SEP-08 09/17/2008 Northbound Traffic Shift Scheduled for Veterans Memorial Tollway (I-355) Resurface & Widen Project
Traffic Will Move to New Pavement Between 75th Street and Ogden Avenue; Work Begins to Rebuild Inside Lanes

[RETURN TO TOP/MENU]

Congestion-Relief Program

This project is part of the Tollway’s multi-billion dollar Congestion-Relief Program. [Learn more...]

Updated October 26, 2009

[RETURN TO TOP/MENU]