Construction Contract Tracker

 

The Illinois Tollway is committed to sharing information regarding construction contracts and expenditures.

The Construction Contract Tracker provides public access to current contract records and information about project status.

Find Explanation of Terms

Jane Addams Memorial Tollway (I-90)

Contract Name and Number Award Amount
I-90 Interchange Reconstruction - IL Route 25
I-13-4104
$11,757,700
I-90 Fox River Bridge
I-13-4144R
$75,412,944
I-90 Bridge Reconstruction - Roselle Road
I-13-4166
$22,391,151
I-90 Bridge Reconstruction - Meacham Road
I-13-4168
$22,949,997
I-90 Reconstruction and Widening - IL Rt 31 to Fox River
I-14-4204
$30,856.653
I-90 Reconstruction and Widening - IL Rt 25 to Higgins Road
I-14-4205
$76,879,371
I-90 Reconstruction and Widening - Higgins Road to Roselle Road
I-14-4206
$77,887,661
I-90 Reconstruction and Widening - Roselle Road to IL Rt 53
I-14-4207
$71,104,729
I-90 Reconstruction and Widening - IL Rt 53 to Arlington Heights Road
I-14-4208
$74,047,592
I-90 Reconstruction and Widening - Arlington Heights Road to Oakton Street
I-14-4209
$62,267,407
I-90 Widening and Reconstruction - Oakton Street to Wolf Road
I-14-4210
$54,880,569
I-90 Widening and Reconstruction - Wolf Road to Mannheim Road
I-14-4211
$46,754,351
I-90 Widening and Reconstruction - Mannheim Road to Kennedy Expressway
I-14-4212
$60,281,636
I-90 Barrington Road Interchange Improvements
I-14-4220
$34,374,868
Intelligent Transportation System Infrastructure Installation
I-15-4227R
$26,046,535
I-90 Widening and Reconstruction - Elgin Toll Plaza to Fox River
I-15-4231
$21,105,929
I-90 Widening and Reconstruction - IL Rt 25 to Higgins Road
I-15-4232
$30,349,821
I-90 Widening and Reconstruction - Higgins Road to Roselle Road
I-15-4233
$40,990,755
I-90 Widening and Reconstruction - Roselle Road to IL Rt 53 & Meacham Interchange
I-15-4234
$27,197,286
I-90 Widening and Reconstruction - IL Rt 53 to Arlington Heights Road
I-15-4235
$39,338,028
I-90 Widening and Reconstruction - Arlington Heights Road to Oakton Street
I-15-4236
$32,112,429
I-90 Widening and Reconstruction - Oakton Street to Mannheim Road
I-15-4237
$58,722,801
I-90 Landscaping Improvements - Genoa Road
I-15-4245
$1,580,422
Rockford Maintenance Facility (M-7) Replacement
RR-16-4258
$25,795,281
I-90 Roadway and Bridge Repairs - US Rt 20 to Randall Road
I-16-4261
$1,843,769
I-90 Barrington Road Pedestrian Overpass Bridge
I-16-4264
$7,057,074
I-90 IL Rt 23 Bridge Widening & Reconstruction
I-16-4268
$6,873,730
NSMJAWA Hot Tap Watermain Relocation - Barrington Road to Elmhurst Road
I-14-4641
$8,159,000
NSMJAWA Watermain Relocation - Elmhurst Road to Higgins Creek
I-14-4648
$18,538,027
I-90 Retaining Wall - Lee Street to Kennedy Expressway
I-13-5679
$13,235,728
I-90 Higgins Road Bridge Reconstruction
I-13-5683
$36,413,114
I-90 Bridge Construction - Barrington Road
I-13-5689
$15,209,546
I-90 Widening and Reconstruction - Higgins Road Bridge and IL Rt 72
I-14-5698
$6,036,713
I-90 Widening and Reconstruction - Tripp Road Bridge and Spring Center Road Bridge
I-14-5700
$6,503,132
I-90 Bridge Rehabilitation - Des Plaines River Road to the Kennedy Expressway
RR-15-5711
$9,169,227
I-90 Bridge & Ramp Repairs - Rockton Road to Spring Creek Road
RR-16-5715
$3,379,021

Elgin O'Hare Western Access

Contract Name and Number

Award
Amount

Reconstruct and Widen Elgin O'Hare Expressway - Meacham Road to Rohlwing Road
I-13-4601

$30,540,953
Elgin O'Hare Western Access - I-290 & Rohlwing Road Interchange Ramps
I-13-4607
$63,973,529
EOWA - Elmhurst Road & Oakton Street Intersection
I-13-4617
$7,280,156
Elgin O'Hare Western Access -Elmhurst Road West Bridge and Interchange
I-13-4618
$29,837,596
Pine Dunes Forest Preserve Wetlands Enhancement and Restoration
I-13-4619
$9,335,000
EOWA - Local Roadway Improvements 
I-13-4621
$4,887,978
EOWA - IL Rt. 390 Construction - Park Boulevard to Arlington Heights Road
I-13-4629
$59,117,000
Elgin O'Hare Western Access - Construction of IL Rt. 390 Bridges over Lively Blvd.
I-13-4630
$14,670,337
EOWA - Salt Creek and Mittel Blvd Bridges
I-13-4631
$18,336,563
Elgin O'Hare Western Access - Building Removal
I-14-4632
$2,328,180
ITS Installation -- Lake Street to IL Rt 83
I-14-4638
$5,325,571
EOWA - Wood Dale Road Bridge over IL Rt 390
I-14-4640
$19,977,569
EOWA - Bridge & Roadway Construction - Prospect Avenue to Lively Blvd
I-14-4642
$52,973,667
EOWA - IL Rt. 390 Construction - Lively Boulevard to Thomas Drive
I-14-4644
$51,160,387
EOWA - Building Removal and Site Clearing
I-15-4649
$3,945,420
EOWA - Landscape Improvements - Lake Street to Rohlwing Road
I-15-4651
$1,323,776
EOWA - Industrial Building Removal in Franklin Park
I-15-4652
$866,429
EOWA - Building Removal - Franklin Park 
I-15-4661
$910,850
EOWA - Advanced Earthwork & Frontage Roads - Supreme Drive to York Road
I-15-4662
$23,058,290
EOWA - Roadway Drainage - Franklin Park
I-15-4663  
     
$9,423,010
EOWA - Roadway Drainage - Plum Grove Road to Meacham Road
I-15-4664
$1,397,341
EOWA - Building Removal
I-16-4665
$726,983

Explanation of Terms

  • Contract Number: Number assigned to contract
  • Description: Scope of work
  • Notice to Proceed: Date in which contractor is able to begin work related to the contract
  • Start Date: Date in which contractor is on-site and beginning work
  • Contract Completion Date: Estimated completion date
  • Contract Award Amount: Original amount Board of Directors approved to be spent on contract
  • Contract Authorized Amount: Amount approved based on original award amount and any change orders or extra work orders applied to contract
  • Board Approval Date: Date in which the Illinois Tollway Board of Directors approved the contract
  • DBE Advertised Goal: Diversity staff establishes specific numerical contract goals for participation of DBE/MBE/WBE certified firms on construction contracts and professional service contracts
  • Project Phase: Phase the contract is currently in
  • Route: Illinois Tollway corridor in which contract is located
  • Location: Contract limits defined by mile posts
  • County: County(ies) in which the contract is located
  • Prime Contractor: Contractor responsible for the completion of the contract
  • Earned to Date: Amount which has been paid out by the Illinois Tollway on the contract
  • Percent Complete: Percentage based on earned to date amount compared to the authorized amount
  • Extra Work Order: Adding new work to a project that was not included in the original contract
  • Change Order: Adding or subtracting quantities of work or materials on a contract